由于受地质、气候等因素的影响,小湾水电站工程施工中某些项目的指标消耗超常,且变动幅度较大。为了客观真实地反映工程成本,同时满足工程建设投资控制和施工管理的需要,对部分正在施工的特性项目进行了定额测定,通过现场写实和分析整理使业主对特殊地质条件和复杂施工环境下的费用支付和进度考核有了一定认识并为加强工程建设管理和投资控制提供了支持性资料。
Due to the influence of geology, climate and other factors, the indicators of some projects in the construction of the Xiaowan Hydropower Station are abnormally consumed and fluctuate greatly. In order to objectively and truly reflect the cost of the project while meeting the investment control and construction management needs of the construction project, part of the project under construction has been measured in a fixed manner. Through the field factualization and analysis and consolidation, the owners are encouraged to evaluate the special geological conditions and complex construction environment The payment of fees and progress assessment have a certain understanding and provide supportive information for strengthening construction management and investment control.