介绍北京地铁10号线03合同段轨道工程施工过程中控制施工进度的主要元素,通过采取增设铺轨基地、新增作业面和人工散铺作业等措施在工期大幅缩短的施工条件下,提高日施工进度,保证了轨道铺设工程按期完成。
This article introduces the main elements of the progress of construction control during the construction of the track section of the 03 Subway Line 03 Contract of Beijing Subway Project. By means of additional laying track bases, new working surfaces and manual spreading operations, under the construction conditions with a drastically shorter construction period, Progress, to ensure that the track laying project completed on schedule.